what we Can
Our Projects:
Project Name |
Clients |
Location |
Contract Values |
Scope of Works |
Duration-Date |
NIPC, Arvand Petrochemical Company |
Arvand Area |
USD 2,000,000 |
Supply of materials |
20 months, |
|
NIPC,Marun Petrochemical Company |
Marun |
USD 1,000,000 |
Procurement of civil parts and equipment |
12 months |
|
Full Procurement of C2 Recovery Temporary Utility |
NIPC, Mobin Petrochemical Company |
Asaluyeh |
USD 8,125,000 |
mechanical and electrical equipment for the project |
7 Monthst 2003 |
n/a |
NIOC, NISOC, MODPC |
n/a |
IRR 1,212,000,000 |
Supply of KCS pipes |
4 months (2008) |
n/a |
NIOC, NISOC, MODPC |
n/a |
IRR 84,000,000,000 |
Supply of pipes |
7 months (2013) |
n/a |
NIOC, NISOC, KOGPC |
n/a |
IRR 2,500,000,000 |
Supply of fittings |
2 months (2013) |
Ahwaz Central Desalting Plant Project |
NIOC, NISOC, |
Ahwaz |
USD50.000.000 |
Supply and procurement of all parts and components |
in progress |
Karanj Parsi Desalting Project |
NIOC, NISOC, |
|
USD 2,600,000 |
Partial procurement of valves, pipes, safety items |
48 months, 2006 |
NIOC, ICOFCO |
Sarvestan Shiraz |
USD 3,000,000 |
Partial supply of parts (control valves, on/off valves, LBV) |
1Year |
|
Lab Sefid Desalting Plant Project |
NISOC |
Asaluyeh |
USD 1,500,000 |
Instruments, in-plant pipes, valves, control , safety, on/off valves |
48 months |
n/a |
NIGC, South Pars Gas Co (SPGC) |
khozestan |
IRR 410,000,000 |
Supply of GRP Pipes |
1.5 months |
n/a |
NIGC , North Khorasan Gas Co. |
Khorasan |
IRR 28,180,000,000 |
Supply of 10" and 12" pipes |
6 months (2009) |
n/a |
Ministry of Power , North Khorasan Water and Waste Water Co. |
North Khorasan |
IRR 4,000,000,000 |
Supply of fiberglass pipes and fittings |
n/a |
Iran Power Plant Projects Management (MAPNA) Construction and Development II |
Yazd |
USD 3,500,000 |
Procurement of BOP equipment including mechanical and electrical tools |
24 month - 2004 |
|
Iran Power Plant Projects Management (MAPNA) Construction and Development II |
Yazd |
USD 3,800,000 |
Procurement of BOP equipment including mechanical and electrical tools |
24 Months |
|
Tishreen Combined Cycle , Power Plant |
Iran Power Plant Projects Management (MAPNA) Construction and Development II |
Syria, Tishreen |
USD 1,700,000 |
Procurement of BOP Equipment and spare parts for Tishreen Combined Cycled Power Plant |
24 Months |
n/a |
Bank Parsian |
Tehran |
USD 1,050,000 |
Supply of Servers |
2006 |
n/a |
Zamyad |
Tehran |
USD 120,000,000 |
Financing and Sourcing Parts for Automotive Industry |
2003 |
n/a |
Irsa Trading Communication |
Tehran |
USD 700,000 |
Supply of Car audio Systems |
11 Months 2013 |
Manufacturing of 3 units of 35, 60 and 160 Double Boom Cranes |
ISOICO |
Bandar Abbas |
USD 10,000,000 |
Procurement and supply of material plus electrical and control system |
2005 |
n/a |
IRICO |
Tehran |
IRR 2,600,000,000 |
Suppy of UPN channels |
2.5 months (2011) |